These entries need to be added to your calendar. Any volunteers? --Kirk 21:01, 17 May 2007 (MDT) Entries have been added to calendar Pradeep 09:31, 22 July 2007 (MDT)Pradeep

10 June: Interface Tables due.
     - Add subsystem requirements to ProtoForge.
1 July: Begin System Requirements Review (SRR).
     - Vote/baseline major requirements.
22 July: End voting phase of SRR. Begin allocation/verification phase of SRR.
     - Allocate requirements to subsystems, list verification methods.
5 Aug: End SRR. Begin IAC paper.
     - Begin the design phase of SEDSAT-2.
15 Aug: completion of first draft
26 Aug: End/upload IAC paper. Begin creating IAC presentation. Begin creating IDM presentation.
1 Sept: End/upload IAC presentation. (the official final date)
16 Sept: End/upload IDM presentation. (updates etc. - you can do this till the last day of presentation)
22 Sept: IDM.